Focus On Water Division
Pay For Performance
Site Progress Summary

Site Name: Tomlinson Oil
UG# 12149-DWT-1200
Posting Date: Mar 10, 2006
Bid Submittal Deadline: May 5, 2006
Contractor Selected: Versar
Bid Price: 158,000.00
Methodology: Oxygen Diffusion
Time of Contract: 24 Months

Contract Type: COC
Contract Start Date: Aug 20, 2006
Milestones Achieved
1. Start up Mar 9, 2007
2. 25% Reduction May 15, 2009
3. 50% Reduction May 15, 2009
4. 75% Reduction May 15, 2009
5. SSTLs or No Free Product Jul 21, 2010
6. One Year Monitoring Start Date Jul 21, 2010
7. Held SSTLs or No FP
8. Equipment Removal/Site Restoration/ Final Payment
Warranty Period (if needed)
Date Warranty Period Started Aug 20, 2008
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP No
Comments:
The site did not meet the final SSTLs. Contract terminated.